Depreciation report example: what a BC report contains, section by section

Most owners see a depreciation report for the first time as a thick PDF attached to a Form B. It is far easier to read once you know its standard parts, which are set out in Regulation 6.2. Here is a walk-through with illustrative tables.

Last reviewed November 19, 2026, against the current Strata Property Act, Strata Property Regulation and Standard Bylaws on BC Laws.

The short answer

A BC depreciation report must contain (Strata Property Regulation 6.2): an executive summary; a physical component inventory and evaluation from an on-site visual inspection, giving each component's estimated service life over 30 years; a summary of repairs and maintenance that occur less than once a year; a 30-year financial forecast with its assumptions (inflation and interest rates), the current reserve balance and how it is funded; at least three cash-flow funding models; and the preparer's name, qualifications, insurance and relationship to the strata. It must be prepared by a qualified person from one of six listed professions.

The required sections

SectionWhat it contains
Executive summaryKey findings, reserve balance, recommended funding model
Component inventory and evaluationEvery major component the strata maintains, its condition, and estimated service life over 30 years
Repairs and maintenance summaryWork that occurs less often than once a year, or that does not usually occur
Financial forecast30 years of anticipated maintenance, repair and replacement costs
AssumptionsInterest and inflation rates used in the forecast
Reserve fund statusHow the reserve is funded now, and its current balance less approved spending
Funding modelsAt least three 30-year cash-flow models, which may use reserve contributions, special levies and borrowing
Preparer detailsName, qualifications, errors and omissions insurance, relationship to the strata
Owner-maintained itemsCommon and limited common property that owners, not the strata, must maintain
DateWhen the report was prepared

These come from Regulation 6.2. The component list must cover the structure, exterior (roofs, doors, windows, skylights), systems (electrical, heating, ventilation, plumbing, fire protection, security), amenities, parking and roadways, utilities, landscaping, interior finishes, green building components, and balconies and patios.

Sample component table

An illustrative extract for a 1998 wood-frame building (figures are examples only):

ComponentConditionRemaining lifeNext workEstimated cost
Asphalt shingle roofFair4 yearsReplace 2030$310,000
Vinyl windowsFair9 yearsReplace 2035$640,000
Exterior paint and sealantsPoor1 yearRepaint 2027$95,000
Boiler and domestic hot waterFair6 yearsReplace 2032$120,000
Elevator modernizationGood12 years2038$180,000
Parkade membraneFair7 yearsReplace 2033$150,000
Fire alarm panelGood10 yearsReplace 2036$40,000

Read the remaining life and next work columns first. They show what is coming in the next five to ten years, which is when special levies happen.

StrataMinutes can take this off your plate. Repair and approval decisions come back years later. Minutes that record them properly are your protection. Have them prepared for you, free for the first month.

Sample funding models

The three models usually differ in how much is saved each year and whether levies or loans fill gaps:

ModelAnnual reserve contributionSpecial levies over 30 yearsLowest reserve balance
A: Current funding$35,000, rising with inflationSeveral large levies, first in year 4Below zero without levies
B: Gradual increase$35,000 rising to $110,000 over 5 yearsOne small levy in year 4About $40,000
C: Full funding$120,000 from year 1NoneAbout $150,000

Council and owners pick a model through the budget. Choosing model A is choosing future special levies. Record which model was adopted, and why, in the minutes.

How to read one in 15 minutes

  1. Executive summary: the recommended model and the current balance.
  2. Next five years in the component table: the big-ticket items.
  3. Funding models: compare the current contribution with the recommended one. A large gap means fee increases or levies ahead.
  4. Assumptions: an unusually low inflation rate makes the plan look easier than it is.
  5. Date: a report older than five years is out of date for stratas with five or more lots.
  6. Minutes: check whether council actually adopted a model and scheduled the work.

Who can prepare it, and when

For reports obtained on or after July 1, 2025, the preparer must be one of: a professional engineer or professional licensee engineering; an architect or architectural technologist; an applied science technologist or certified technician; an Accredited Appraiser Canadian Institute; a certified reserve planner accredited by the Real Estate Institute of Canada; or a Professional Quantity Surveyor (Regulation 6.2). Stratas with five or more lots need an updated report at least every five years. See depreciation reports for deadlines and depreciation report providers.

Questions councils and owners ask

What does a depreciation report contain in BC?

An executive summary, a component inventory from a site inspection with service lives over 30 years, a repairs summary, a 30-year forecast with assumptions, the reserve balance, at least three funding models, and the preparer's details (Regulation 6.2).

How many funding models must a depreciation report have?

At least three 30-year cash-flow funding models, which may include reserve contributions, special levies and borrowing.

Who can write a depreciation report in BC?

For reports obtained on or after July 1, 2025, a member of one of six listed professions, including professional engineers, architects, certified reserve planners and professional quantity surveyors.

How do I read a depreciation report quickly?

Start with the executive summary, then the next five years of component work, then compare the current reserve contribution with the recommended funding model.

Is an electrical planning report the same as a depreciation report?

No. It is a separate report under section 94.1 about the building's electrical capacity and future needs, with its own deadlines.

The report is only useful if council acts on it

Decisions to adopt a funding model, schedule work and spend from the reserve belong in the minutes. StrataMinutes records them properly from your notes.

Try your first month free

Free for 30 days, then $29 a month. Cancel anytime.

For a 30-lot strata, that is under $1 a lot each month. Have the strata pay: free council approval kit.

This page is general information for BC strata corporations, not legal advice. Your strata's own filed bylaws may differ from the Standard Bylaws. See the current text of the Strata Property Act and the Strata Property Regulation on BC Laws.